Consider the schedule R1(B), W3(B), W3(A), R2(B), W2(A), R1(A), W1(A). Which statement is correct?

  1. A. Conflict serializable, equivalent to T3 → T2 → T1
  2. B. It is not conflict serializable
  3. C. Conflict serializable, equivalent to T2 → T1 → T3
  4. D. Conflict serializable, equivalent to T1 → T3 → T2

Correct answer: B. It is not conflict serializable

The precedence graph has both T3 → T1 and T1 → T3 (a cycle), so no serial order exists.