CS FundamentalsHardGATE CS · Product placement
Consider the schedule W3(C), W2(A), W1(A), R1(C), R2(A), R2(C), W3(A). Which statement is correct?
- A. Conflict serializable, equivalent to T3 → T2 → T1
- B. Conflict serializable, equivalent to T1 → T2 → T3
- C. It is not conflict serializable
- D. Conflict serializable, equivalent to T2 → T1 → T3
Correct answer: C. It is not conflict serializable
The precedence graph has both T1 → T2 and T2 → T1 (a cycle), so no serial order exists.
More DBMS and SQL questions
- A B+ tree index uses 1024-byte blocks, 10-byte search keys, 6-byte block (tree) pointers and 8-byte record pointers. What is the maximum…
- R(A, B, C, D, E) has functional dependencies E → B, B → A, D → B, A → D. Which decomposition of R is lossless-join?
- R(A, B, C, D, E) with functional dependencies B → C, D → CE, A → B, CE → A is decomposed into R1(A, B), R2(A, C, E), R3(C, D, E). Which…
- Which inference rule is NOT sound for functional dependencies?
- Table Staff(id, name, dept, pay, boss) rows: (1, 'Anu', 'Ops', 40, NULL), (2, 'Bala', 'Ops', 55, 1), (3, 'Chitra', 'Tech', 70, 1), (4…
- Consider the schedule W1(B), W2(A), R2(A), W1(A), R3(A), W3(B). Which statement is correct?