Classify the schedule R1(X), W2(X), W1(X), W3(X), R4(X).

  1. A. Conflict serializable, equivalent to T2 T1 T3 T4
  2. B. View serializable (as T1 T2 T3 T4) but not conflict serializable
  3. C. Neither conflict nor view serializable
  4. D. Conflict serializable, equivalent to T1 T2 T3 T4

Correct answer: B. View serializable (as T1 T2 T3 T4) but not conflict serializable

R1(X) → W2(X) and W2(X) → W1(X) form a cycle, so it is not conflict serializable. In T1 T2 T3 T4, T1 reads the initial X, T4 reads T3's write and T3 writes last, exactly as here; the blind writes make the views match.