Data Structures & AlgorithmsVery hardGATE CS · TCS NQT
Four jobs need 5, 3, 4 and 1 units of time; a round-robin scheduler gives each job one unit per turn in queue order and removes finished jobs. What is the sum of the completion times of the four jobs?
- A. 39
- B. 38
- C. 37
- D. 13
Correct answer: B. 38
Simulate the round-robin queue one unit at a time, recording the time each job finishes. The jobs of length 1, 3, 4 and 5 finish at times 4, 9, 12 and 13, so the sum is 38.
Practise more Arrays, Strings, Linked Lists, Stacks, Queues and Hashing questionsArrays, Strings, Linked Lists, Stacks, Queues and Hashing: notes and key points
More Arrays, Strings, Linked Lists, Stacks, Queues and Hashing questions
- How many windows of size 3 in [1, 3, 2, 6, 4, 5, 1] have max minus min at most 2?
- How many integers from 1 to 50 inclusive have a digit sum that is divisible by 5?
- What is the minimum value of a[i] XOR a[j] over index pairs i < j in [15, 2, 19, 6, 11, 9]?
- How many integers from 1 to 40 inclusive have exactly as many 0-bits as 1-bits in their binary representation (without leading zeros)?
- Four jobs given as (deadline, processing time) are (2, 3), (4, 2), (5, 6), (7, 4) and run one after another from time 0. Order them by…
- What is the length of the longest substring of "pwwkewbcab" with no repeated characters?