Data Structures & AlgorithmsVery hardCodeforces Div2 B-D · ICPC regional

Tasks are (duration, deadline): (4, 2), (2, 1), (3, 2), (1, 1), (5, 3), and a single machine runs them one at a time from time 0. What is the maximum number of tasks that can finish by their deadlines?

  1. A. 1
  2. B. 2
  3. C. 0
  4. D. 5

Correct answer: A. 1

Process tasks in deadline order and, whenever the running total overruns, drop the longest task so far (a heap of durations). This exchange keeps as many tasks as possible.