Data Structures & AlgorithmsVery hardCodeforces Div2 B-D · ICPC regional
Five jobs given as (processing time, deadline) are (4,4), (2,2), (3,3), (1,1), (6,7). You run them in some order, and a job is late if it finishes after its deadline. What is the minimum number of late jobs?
- A. 3
- B. 4
- C. 2
- D. 5
Correct answer: A. 3
Moore-Hodgson: sort by deadline, keep a max-heap of accepted durations, and drop the largest when the schedule overruns. The dropped jobs are the late ones, which are the minimum possible.
Practise more Arrays, Strings, Linked Lists, Stacks, Queues and Hashing questionsArrays, Strings, Linked Lists, Stacks, Queues and Hashing: notes and key points
More Arrays, Strings, Linked Lists, Stacks, Queues and Hashing questions
- How many index pairs i < j in [4, 1, 5, 3, 2, 6] satisfy 0 < a[i] - a[j] <= 2?
- From the windows of length 3 of [3, 9, 2, 8, 1, 7], remove the smallest element of the chosen window and maximise the sum that remains…
- What is the sum of (max minus min) over all windows of size 3 in [2, 7, 1, 8, 2]?
- What is the smallest positive integer x such that the sum of floor(x / ai) over a = [2, 3, 5] is at least 20?
- What is the lexicographically smallest subsequence of length 3 of "cbacdcbc"?
- How many positive divisors of 2^5 3^2 7 are odd?