Data Structures & AlgorithmsHardGATE CS · ICPC regional

Five jobs (processing time, due date) are [(4, 9), (2, 6), (6, 12), (3, 7), (5, 10)]. They run one at a time with no preemption, starting at time 0 in any order you choose. What is the smallest possible maximum lateness (max of completion time − due date)?

  1. A. 8
  2. B. 10
  3. C. 20
  4. D. 9

Correct answer: A. 8

Earliest Due Date (EDD) order is optimal for maximum lateness: sort by due date and run the jobs back to back. Shortest-processing-time order minimises total completion time, not lateness, and can make the job with the earliest due date finish last.