A project has a budget at completion (BAC) of ₹400 lakh. At the end of month 5 the planned value is ₹180 lakh, the earned value ₹150 lakh and the actual cost ₹200 lakh. What are the cost performance index, the schedule performance index and the estimate at completion (assuming current cost efficiency continues)?

  1. A. CPI 0.90, SPI 0.75, EAC about ₹444 lakh
  2. B. CPI 0.75, SPI 0.83, EAC about ₹533 lakh
  3. C. CPI 1.33, SPI 1.20, EAC about ₹300 lakh
  4. D. CPI 0.75, SPI 0.83, EAC ₹450 lakh

Correct answer: B. CPI 0.75, SPI 0.83, EAC about ₹533 lakh

CPI = EV/AC = 150/200 = 0.75: each rupee spent earns 75 paise of planned work. SPI = EV/PV = 150/180 = 0.83: behind schedule. EAC = BAC/CPI = 400/0.75 = about ₹533 lakh. Inverting the ratios gives 1.33 and 1.20, which would wrongly suggest the project is ahead. ₹450 lakh is AC + (BAC - EV), which assumes the rest of the work will suddenly go to plan; CPI 0.90 compares PV with AC, which mixes up the two indices.

More Software Engineering, Git and Cloud Basics questions

Exams that ask this topic