CS FundamentalsVery hardProduct company interview · GATE level
A project has a budget at completion (BAC) of ₹400 lakh. At the end of month 5 the planned value is ₹180 lakh, the earned value ₹150 lakh and the actual cost ₹200 lakh. What are the cost performance index, the schedule performance index and the estimate at completion (assuming current cost efficiency continues)?
- A. CPI 0.90, SPI 0.75, EAC about ₹444 lakh
- B. CPI 0.75, SPI 0.83, EAC about ₹533 lakh
- C. CPI 1.33, SPI 1.20, EAC about ₹300 lakh
- D. CPI 0.75, SPI 0.83, EAC ₹450 lakh
Correct answer: B. CPI 0.75, SPI 0.83, EAC about ₹533 lakh
CPI = EV/AC = 150/200 = 0.75: each rupee spent earns 75 paise of planned work. SPI = EV/PV = 150/180 = 0.83: behind schedule. EAC = BAC/CPI = 400/0.75 = about ₹533 lakh. Inverting the ratios gives 1.33 and 1.20, which would wrongly suggest the project is ahead. ₹450 lakh is AC + (BAC - EV), which assumes the rest of the work will suddenly go to plan; CPI 0.90 compares PV with AC, which mixes up the two indices.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- Under Musa's basic execution-time model, failure intensity falls linearly with failures experienced: λ(μ) = λ0 (1 - μ/ν0), and over…
- Defects injected: 40 during requirements, 60 during design and 100 during coding. A requirements review removes 50% of the defects present…
- A class has fields a, b, c, d, e and methods m1 (uses a, b), m2 (uses b, c), m3 (uses d) and m4 (uses d, e). Using the Chidamber-Kemerer…
- main has commits A-B-C-D-E (E is main's tip). feature was created at C and got commits F and G; then main was merged into feature…
- A service runs on 3 identical servers, each 95% available and failing independently; it works when at least 2 of the 3 are up (a majority…
- A system needs all three of its components to work. Their failure times are exponential with MTTFs of 2,000, 5,000 and 10,000 hours. What…