A code inspection proceeds at 150 lines per hour in the meeting with 4 inspectors present. How much meeting effort does inspecting 3,000 lines take?
- A. 20 person-hours
- B. 80 person-hours
- C. 5 person-hours
- D. 600 person-hours
Correct answer: B. 80 person-hours
Meeting time = 3,000/150 = 20 hours, and with 4 people that is 80 person-hours. 20 is the calendar time of the meeting, not the effort.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A function-point estimate and a COCOMO estimate for the same project differ widely. Which statement best explains why function points are…
- A team measures defect density after release. Release 1: 30 defects in 15 KLOC. Release 2 adds 10 KLOC of new code and has 26 defects, all…
- Activities (days; predecessors): P 5 (-), Q 6 (-), R 5 (P), S 5 (Q), T 4 (R, S). The manager can shorten only one activity by 2 days…
- Counting each simple condition separately (each 'and'/'or' adds one) and each loop header as one decision, what is the cyclomatic…
- For the function below, which single call executes every statement (100% statement coverage)? python def f(a, n): total = 0 for x in a: if…
- For the call f([3], 5) on the function below, what decision (branch) coverage is achieved, treating the for loop as a decision with two…