Using MoSCoW for a fixed-date release, the team runs out of time. Which items are dropped first, and what does 'Won't have' mean?

  1. A. Could-haves are dropped first; Won't-have means not in this release, though it may come later
  2. B. Must-haves are dropped first; Won't-have items are cancelled forever
  3. C. Should-haves are dropped first; Won't-have means low quality
  4. D. Items are dropped at random; Won't-have means rejected by the customer

Correct answer: A. Could-haves are dropped first; Won't-have means not in this release, though it may come later

Could-haves are the first contingency, then Should-haves if needed; Musts define the minimum viable release. 'Won't have (this time)' records agreed out-of-scope items, which manages expectations.