Using MoSCoW for a fixed-date release, the team runs out of time. Which items are dropped first, and what does 'Won't have' mean?
- A. Could-haves are dropped first; Won't-have means not in this release, though it may come later
- B. Must-haves are dropped first; Won't-have items are cancelled forever
- C. Should-haves are dropped first; Won't-have means low quality
- D. Items are dropped at random; Won't-have means rejected by the customer
Correct answer: A. Could-haves are dropped first; Won't-have means not in this release, though it may come later
Could-haves are the first contingency, then Should-haves if needed; Musts define the minimum viable release. 'Won't have (this time)' records agreed out-of-scope items, which manages expectations.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- Assertion (A): Agile teams still write documentation. Reason (R): The Agile Manifesto values working software over comprehensive…
- A consultancy must build a regulatory reporting system for a bank. The rules are fixed by law and fully specified, the deadline is firm…
- A Kubernetes Deployment has 10 replicas and a rolling-update strategy with maxSurge = 25% and maxUnavailable = 25%. Kubernetes rounds…
- A team wants to rename the column custname to customername in a live database with zero downtime while old and new app versions run side…
- A Dockerfile ends with ENTRYPOINT ["python", "app.py"] and CMD ["--port", "80"]. The container is started with docker run myimg --port…
- A Go service's Docker image is 900 MB because it includes the compiler and build tools. Which change gives a small image containing only…