CS FundamentalsHardInfosys · ISTQB-style
Which set of exit criteria is most appropriate for ending a system-test cycle?
- A. All planned tests have been executed, no open critical or high-severity defects remain, requirement coverage meets the target and residual risks are accepted by stakeholders
- B. The test team has used its allotted days
- C. The developers say the code is ready
- D. At least one test case per module passed
Correct answer: A. All planned tests have been executed, no open critical or high-severity defects remain, requirement coverage meets the target and residual risks are accepted by stakeholders
Exit criteria should be objective and agreed in the test plan: execution and coverage targets, defect thresholds and an explicit risk decision. Time alone or a developer's opinion is not a quality criterion.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- Before go-live, the operations team checks that backups restore correctly, failover works, monitoring alerts fire and the system can be…
- In session-based exploratory testing, what defines a session?
- Which statement about integration-testing strategies is correct?
- Defect data from the last three releases shows that 80% of all defects came from 2 of the system's 12 modules. Which principle should…
- How many of these statements about testing in production are correct? 1. A dark launch runs new code paths in production without showing…
- A test suite of 5 tests detects 4 faults. The fault-revealing positions in the execution order are: fault 1 by test 1, fault 2 by test 2…