CS FundamentalsHardCognizant · Capgemini pattern
A Scrum team's last three sprints delivered 28, 32 and 30 story points. 240 points remain in the backlog and sprints are 2 weeks long. Using average velocity, about how long will the remaining work take?
- A. 16 weeks
- B. 8 weeks
- C. 15 weeks
- D. 24 weeks
Correct answer: A. 16 weeks
Average velocity = (28 + 32 + 30)/3 = 30 points per sprint. 240/30 = 8 sprints × 2 weeks = 16 weeks. 8 weeks is the sprint count mistaken for weeks.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- Using basic COCOMO for an organic project (E = 2.4 × KLOC^1.05 person-months), what is the estimated effort for a 32 KLOC project?
- For the code if (x > 0) { y = 1; } followed by print(y), a single test with x = 5 is run. What coverage does it achieve?
- A server has a mean time between failures of 990 hours and a mean time to repair of 10 hours. What is its availability?
- A new build arrives and testers first run a small, broad set of checks (does it install, launch, log in, open the main screens?) before…
- You are halfway through a change when an urgent bug needs fixing on the same branch. Which command shelves your uncommitted changes so the…
- A Dockerfile ends with CMD ["python", "app.py"]. The container is started with docker run myimage python test.py. What runs?