CS FundamentalsHardAccenture · Cognizant
Last sprint, 6 developers working 10 days completed 30 story points. Next sprint 5 developers are available for 9 days each. Using the same points per person-day, what should the team plan for?
- A. About 22.5 points
- B. About 25 points
- C. About 27 points
- D. 30 points
Correct answer: A. About 22.5 points
Rate = 30/(6 x 10) = 0.5 points per person-day; next sprint has 5 x 9 = 45 person-days, so about 22.5 points. Adjusting only for people (25) or only for days (27) misses one factor.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A single-server queue (M/M/1) serves 10 requests per second. At 8 requests/s the mean response time W = 1/(μ - λ) is 0.5 s. What happens…
- 90% of a CI pipeline's run time is parallelisable tests and 10% is serial setup. Moving to 8 parallel runners, what overall speed-up does…
- A suite of 1,200 tests averaging 3 seconds each is split evenly across 6 parallel shards, and each shard needs 2 minutes of setup before…
- A cache answers 90% of reads in 2 ms; on a miss the read takes 50 ms in total (cache check plus database). What is the average read…
- Each web server handles 250 requests/s, but for headroom servers should run at no more than 70% of that. Peak load is 2,000 requests/s and…
- A service stores 2 TB of data with a replication factor of 3, and disks should be kept at most 70% full. How much raw disk capacity is…