CS FundamentalsHardInfosys · Wipro
In software configuration management, the approved requirements specification is frozen and further changes need formal approval by a change control board. What is the frozen version called?
- A. A branch
- B. A tag only
- C. A baseline
- D. A sandbox
Correct answer: C. A baseline
A baseline is a formally reviewed and agreed version of a configuration item that serves as the basis for further work and can be changed only through change control.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A team records, in short version-controlled documents, why it chose PostgreSQL over MongoDB, the context, the options considered and the…
- A request passes through 6 microservices and is sometimes slow. Logs and per-service CPU metrics look normal. Which observability tool…
- A team deliberately terminates random instances and injects latency in production during business hours, with monitoring and a way to stop…
- After a major outage, a team writes a postmortem focusing on what in the system and process allowed the mistake, rather than on who made…
- Assertion (A): Writing the same 'Order' entity into both an orders database and a search index inside one request handler can leave them…
- A team's code review guideline says reviewers should check that each pull request has tests for new behaviour, follows the style guide…