CS FundamentalsHardProduct-company placement · PMP-style
A task has optimistic 4 days, most likely 6 days and pessimistic 20 days. What are the triangular-distribution mean (a + m + b)/3 and the PERT mean (a + 4m + b)/6, and why do they differ?
- A. Both 10 days
- B. Triangular 8 days, PERT 10 days; PERT weights the extremes more
- C. Triangular 10 days, PERT 8 days; PERT puts more weight on the most likely value, so the long tail pulls it up less
- D. Triangular 6 days, PERT 8 days; the triangular mean equals the mode
Correct answer: C. Triangular 10 days, PERT 8 days; PERT puts more weight on the most likely value, so the long tail pulls it up less
(4 + 6 + 20)/3 = 10 and (4 + 24 + 20)/6 = 8. With a skewed range, the choice of model matters; neither equals the most likely 6 days.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- In IFPUG function-point counting, which of these is an external output (EO) rather than an external inquiry (EQ)?
- A database cluster needs each replica to keep a stable network name (db-0, db-1, db-2) and its own persistent volume across restarts…
- In GitOps, how does a change reach a Kubernetes cluster?
- A team stops patching running servers in place and instead builds a new machine image for every change, replacing old servers entirely…
- How many of these statements about cyclomatic complexity are correct? 1. Adding a straight-line statement to a function never changes…
- A team applies the Open/Closed principle so aggressively that every class has an interface, a factory and plug-in points 'in case'…