A Scrum team's velocity over 6 sprints was 20, 22, 35, 21, 23 and 19 points; sprint 3 included a one-off batch of over-estimated stories. For forecasting, which estimate is more robust, and what is it?
- A. The median, 21.5 points, because it is not distorted by the one-off outlier
- B. The mean, about 23.3 points
- C. The maximum, 35 points
- D. The latest sprint, 19 points
Correct answer: A. The median, 21.5 points, because it is not distorted by the one-off outlier
Sorted: 19, 20, 21, 22, 23, 35; median = (21 + 22)/2 = 21.5. The mean (140/6 ≈ 23.3) is pulled up by the outlier; best-case or single-sprint figures ignore variation.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- An enterprise service-level agreement promises 99.95% monthly availability with service credits, the internal SLO is 99.99%, and the…
- A team makes 'Developers must not deploy on Fridays' a rule after two weekend outages. A senior engineer argues the rule treats the…
- A brand-new repository's first commit contains a.txt (content 'hello'), src/b.txt and src/c.txt, where b.txt and c.txt have identical…
- In a hexagonal (ports-and-adapters) architecture, the order-processing core defines an interface OrderRepository, implemented by a…
- A module handleIO(kind, data) contains one big switch: kind 1 reads from the keyboard, kind 2 writes a file, kind 3 sends a network…
- For integer variables, what is the weakest precondition wp(x := x + 1; y := 2 x, y > 10)?