Critical chain project management removes the safety margin from each task estimate and pools it into a project buffer at the end. Which behaviours is this mainly designed to counter?
- A. Student syndrome (starting late) and Parkinson's law (work expanding to fill the time)
- B. Brooks' law and Conway's law
- C. Scope creep and gold plating
- D. Technical debt and code rot
Correct answer: A. Student syndrome (starting late) and Parkinson's law (work expanding to fill the time)
Padded individual estimates tend to be wasted: people start late and fill the time available, so the padding never protects the project. Aggregating it into a shared buffer protects the end date with less total margin.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A rules engine must evaluate business rules such as (age > 18 AND country = 'IN') OR isVip from a small fixed grammar, using one class per…
- Match each module with its type of cohesion. P: computes the mean, maximum and histogram of the same input array. Q: performs one of…
- A media player has states Stopped, Playing and Paused and events play, pause and stop. Valid transitions: Stopped–play→Playing…
- A UML class diagram says each Course has 1..3 Instructors and each Instructor teaches 0..4 Courses (many-to-many). Which configuration is…
- A company split its monolith into 12 microservices, but every release still needs all 12 deployed together in a fixed order, and several…
- A gRPC API's Protocol Buffers message had field 'int32 discount = 4', which was deleted last year. A developer now adds 'string coupon =…