Critical chain project management removes the safety margin from each task estimate and pools it into a project buffer at the end. Which behaviours is this mainly designed to counter?

  1. A. Student syndrome (starting late) and Parkinson's law (work expanding to fill the time)
  2. B. Brooks' law and Conway's law
  3. C. Scope creep and gold plating
  4. D. Technical debt and code rot

Correct answer: A. Student syndrome (starting late) and Parkinson's law (work expanding to fill the time)

Padded individual estimates tend to be wasted: people start late and fill the time available, so the padding never protects the project. Aggregating it into a shared buffer protects the end date with less total margin.