CS FundamentalsHardService-company placement · Agile

A Scrum team keeps pulling stories into sprints that lack acceptance criteria and depend on undecided UX. Which agreement addresses this, and how does it differ from the Definition of Done?

  1. A. A stricter Definition of Done, which would also govern when stories may enter a sprint
  2. B. A Definition of Ready for starting items, distinct from the DoD for finished increments
  3. C. A Sprint Goal listing every story's acceptance criteria before Sprint Planning begins
  4. D. A working agreement that only the Scrum Master may add stories to the sprint backlog

Correct answer: B. A Definition of Ready for starting items, distinct from the DoD for finished increments

A Definition of Ready is a team-level convention for refinement (clear, estimated, unblocked), not a Scrum Guide artifact; the Definition of Done is the formal quality bar an Increment must meet.