A team can (A) build a module in-house: 60% chance of gaining ₹50 lakh and 40% chance of losing ₹20 lakh; (B) buy a licence for a certain gain of ₹18 lakh; or (C) partner: 50% chance of ₹40 lakh and 50% chance of nothing. Which option has the highest expected monetary value?

  1. A. B, ₹18 lakh
  2. B. C, ₹20 lakh
  3. C. A, ₹30 lakh
  4. D. A, ₹22 lakh

Correct answer: D. A, ₹22 lakh

EMV(A) = 0.6 × 50 − 0.4 × 20 = 22; EMV(C) = 0.5 × 40 = 20; EMV(B) = 18. So A wins at ₹22 lakh. ₹30 lakh forgets to subtract the possible loss.