Match each risk response with an example. P. Avoid Q. Transfer R. Mitigate S. Accept 1. Buy fixed-price insurance against data-centre damage. 2. Drop an untested third-party library from the design. 3. Add load tests early to reduce the chance of a slow launch. 4. Note a minor UI-font risk and handle it only if it occurs.

  1. A. P-1, Q-2, R-3, S-4
  2. B. P-2, Q-1, R-4, S-3
  3. C. P-3, Q-1, R-2, S-4
  4. D. P-2, Q-1, R-3, S-4

Correct answer: D. P-2, Q-1, R-3, S-4

Avoidance removes the cause (drop the library); transfer shifts the impact to someone else (insurer or contractor); mitigation reduces probability or impact (early load tests); acceptance consciously takes the risk.