CS FundamentalsVery hardService-company placement · GATE CS
Intermediate COCOMO for an organic project uses Effort = 3.2 × KLOC^1.05 × EAF person-months. A 30 KLOC system has two non-nominal cost drivers, 0.85 and 1.15, and a person-month costs ₹2 lakh. What is the estimated development cost?
- A. About ₹228 lakh
- B. About ₹222 lakh
- C. About ₹171 lakh
- D. About ₹111 lakh
Correct answer: B. About ₹222 lakh
EAF = 0.85 × 1.15 = 0.9775; 30^1.05 ≈ 35.56, so E ≈ 3.2 × 35.56 × 0.9775 ≈ 111 PM, costing ≈ ₹222 lakh. Ignoring EAF gives ₹228 lakh, and using the basic-model coefficient 2.4 gives ₹171 lakh.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- Counting one decision for each loop, if, else-if, && or || operator, case label (not default) and catch clause, what is the cyclomatic…
- For the decision (A or B) and C, which test set (written as A, B, C) achieves MC/DC with only four tests?
- A leap-year function follows the Gregorian rule (divisible by 4, except centuries, unless divisible by 400). Which test set has one year…
- On main, git revert HEAD~3..HEAD is run with no conflicts. What happens?
- main receives feature work only through merge commits (git merge --no-ff), plus a few direct hotfix commits. What does git log…
- What does this code print (lines joined by ' / ')? python handlers = {'+': lambda a, b: a + b} def fallback(): print('fallback') return…