A team has 40 open defects; 15 new ones arrive and 25 are fixed each week. If these rates hold, how long until the backlog is cleared?

  1. A. About 1.6 weeks
  2. B. About 2.7 weeks
  3. C. 4 weeks
  4. D. 10 weeks

Correct answer: C. 4 weeks

The backlog falls by the net rate 25 − 15 = 10 per week, so 40 / 10 = 4 weeks. 1.6 weeks (40/25) ignores new arrivals and 2.7 weeks (40/15) uses the wrong rate.