CS FundamentalsModerateService-company placement
A team has 40 open defects; 15 new ones arrive and 25 are fixed each week. If these rates hold, how long until the backlog is cleared?
- A. About 1.6 weeks
- B. About 2.7 weeks
- C. 4 weeks
- D. 10 weeks
Correct answer: C. 4 weeks
The backlog falls by the net rate 25 − 15 = 10 per week, so 40 / 10 = 4 weeks. 1.6 weeks (40/25) ignores new arrivals and 2.7 weeks (40/15) uses the wrong rate.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- Which statement correctly contrasts a centralised VCS such as Subversion with Git?
- Two artists keep overwriting each other's edits to the same layered .psd file in Git. Why does the usual merge workflow fail, and what…
- Priya rebases Rahul's three commits onto the latest main. What happens to the author and committer fields of the rewritten commits?
- Business rules like 'premium customer AND (order > ₹10,000 OR festive season)' are built as small objects with isSatisfiedBy(candidate)…
- A service reuses expensive database connections from a pool instead of opening one per request. One request leaves a connection inside an…
- Following Beizer's guidance for testing two nested loops, how should you start?