CS FundamentalsVery hardGATE CS · Software Engineering · Advanced

A project has a budget at completion of 800 units. After some time 60% of the work was planned to be complete, 45% is actually complete, and the actual cost so far is 420 units. If the current cost performance is expected to continue for the rest of the project, what is the estimate at completion (EAC)?

  1. A. 860 units
  2. B. 1067 units
  3. C. 686 units
  4. D. 933 units

Correct answer: D. 933 units

EV = 0.45 x 800 = 360 and CPI = EV/AC = 360/420 = 0.857. With typical (continuing) variances EAC = BAC / CPI = 933. BAC + AC - EV = 860 assumes the overrun was a one-off, and BAC / SPI is a schedule estimate.