CS FundamentalsVery hardGATE CS · Software Engineering · Advanced
A project has a budget at completion of 800 units. After some time 60% of the work was planned to be complete, 45% is actually complete, and the actual cost so far is 420 units. If the current cost performance is expected to continue for the rest of the project, what is the estimate at completion (EAC)?
- A. 860 units
- B. 1067 units
- C. 686 units
- D. 933 units
Correct answer: D. 933 units
EV = 0.45 x 800 = 360 and CPI = EV/AC = 360/420 = 0.857. With typical (continuing) variances EAC = BAC / CPI = 933. BAC + AC - EV = 860 assumes the overrun was a one-off, and BAC / SPI is a schedule estimate.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- The decision (A and B) or (C and D) contains four conditions. What is the minimum number of test cases that achieves 100% modified…
- A routine takes three integer inputs a, b, c, each with a valid range [min, max] with min < max - 1, and one boolean flag f. Under…
- A configuration has 4 parameters with 3 possible values each. What is the minimum number of test cases needed to cover every pair of…
- A team of 6 developers is increased to 9 developers to catch up on a late project. If every pair of team members needs one communication…
- A mutation tool generated 60 mutants. Review shows 10 of them are equivalent mutants, and the current test suite kills 30 of the others…
- What is printed? python class S: def init(self): self.obs = [] def notify(self, x): for o in self.obs: o(x) log = [] def a(x)…