A Kanban team's board holds on average 15 items (queued or in progress), and over a long period the team delivers 20 items in every 10 working days. By Little's Law, what is the average time an item spends on the board, from entering to leaving?

  1. A. 15.0 days
  2. B. 30.0 days
  3. C. 7.5 days
  4. D. 10.0 days

Correct answer: C. 7.5 days

Little's Law: average cycle time = WIP / throughput = 15 / (20/10 per day) = 7.5 days. Multiplying instead of dividing (30) or using throughput per fortnight in the wrong unit gives other values.