A Kanban team's board holds on average 15 items (queued or in progress), and over a long period the team delivers 20 items in every 10 working days. By Little's Law, what is the average time an item spends on the board, from entering to leaving?
- A. 15.0 days
- B. 30.0 days
- C. 7.5 days
- D. 10.0 days
Correct answer: C. 7.5 days
Little's Law: average cycle time = WIP / throughput = 15 / (20/10 per day) = 7.5 days. Multiplying instead of dividing (30) or using throughput per fortnight in the wrong unit gives other values.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A method contains 3 if statements, 1 while loop and 1 for loop, with no && or || operators and no other branching. What is its cyclomatic…
- After committing by mistake, a developer runs git reset --soft HEAD~1. What is the result?
- A field accepts ages from 18 to 60 inclusive. Which set of test values best applies boundary value analysis?
- In Scrum, who is accountable for ordering the items in the Product Backlog?
- The question "Are we building the right product?" is answered by which activity?
- Which of the following is a typical example of Platform as a Service (PaaS)?