CS FundamentalsHardTCS NQT · Accenture
A task has optimistic 4 days, most likely 6 days and pessimistic 14 days. What is the PERT expected duration?
- A. 8 days
- B. 6 days
- C. 9 days
- D. 7 days
Correct answer: D. 7 days
Expected time = (O + 4M + P)/6 = (4 + 24 + 14)/6 = 7 days.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- Which deployment strategy releases a new version to a small subset of users first and widens the rollout gradually while monitoring?
- Why is it advised not to run git rebase on commits already pushed to a shared branch?
- A module of 30,000 lines of code has 45 defects found in testing. What is the defect density?
- Under the cloud shared responsibility model for IaaS (for example virtual machines), which task is the customer's responsibility?
- A Square class extends Rectangle and overrides setWidth so that it also changes the height, breaking code that expects independent width…
- A control-flow graph has 20 edges, 16 nodes and 2 connected components. Using V(G) = E - N + 2P, what is the cyclomatic complexity?