For a one-month Sprint, the Scrum Guide's maximum time-boxes are 4 hours for the Sprint Review and 3 hours for the Sprint Retrospective. What is their combined maximum?
- A. 8 hours
- B. 7 hours
- C. 12 hours
- D. 5 hours
Correct answer: B. 7 hours
4 + 3 = 7 hours; the 8 hour figure is the time-box for Sprint Planning, not these events.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A tester re-runs the existing test suite after a developer changes the code, to confirm that previously working features have not broken…
- Which SDLC model completes each phase (requirements, design, coding, testing, deployment) fully before the next one starts, in a strict…
- Which Git command makes a full local copy of a remote repository, including its history?
- In Scrum, who is responsible for ordering (prioritising) the Product Backlog?
- A company uses a web-based email service where the provider runs everything from servers to the application itself. Which cloud service…
- Testing an individual function or class in isolation, usually by the developer who wrote it, is called: