For a one-month Sprint, the Scrum Guide's maximum time-boxes are 4 hours for the Sprint Review and 3 hours for the Sprint Retrospective. What is their combined maximum?

  1. A. 8 hours
  2. B. 7 hours
  3. C. 12 hours
  4. D. 5 hours

Correct answer: B. 7 hours

4 + 3 = 7 hours; the 8 hour figure is the time-box for Sprint Planning, not these events.