CS FundamentalsHardHCL · Tech Mahindra pattern

Before release, 120 defects are found in system testing and 30 in user acceptance testing. After release, customers report 50 more. What is the defect removal efficiency (DRE) of the pre-release testing?

  1. A. 80%
  2. B. 75%
  3. C. 70%
  4. D. 60%

Correct answer: B. 75%

DRE = defects found before release/(before + after) = (120 + 30)/(150 + 50) = 150/200 = 75%. Using only system-test defects (120/200) gives 60%; ignoring UAT in the total (120/170) gives about 70%.