CS FundamentalsModerateTCS NQT · Infosys pattern

In the V-model, acceptance testing is planned against which development phase?

  1. A. Architectural design
  2. B. Detailed (module) design
  3. C. Coding
  4. D. Requirements analysis

Correct answer: D. Requirements analysis

Each left-side phase pairs with a right-side test level: requirements ↔ acceptance testing, system/architectural design ↔ system and integration testing, module design ↔ unit testing.