Using a three-point PERT estimate, a task has optimistic time 4 days, most likely 6 days and pessimistic 14 days. What is the expected duration?
- A. 8 days
- B. 7 days
- C. 6 days
- D. 9 days
Correct answer: B. 7 days
PERT expected time = (O + 4M + P) / 6 = (4 + 24 + 14) / 6 = 7 days. 8 days is the plain average (4 + 6 + 14)/3; 6 days is just the most likely value.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- An application is modified so that it keeps working after the company moves it to a new operating system version and a new database…
- Counts for a system: 10 external inputs, 8 external outputs, 6 external inquiries, 4 internal logical files and 2 external interface…
- What is the minimum number of test cases needed to achieve MC/DC (modified condition/decision coverage) for the decision if (A && B)?
- A method in class Invoice spends most of its code reading fields of a Customer object (name, address, discount tier) and barely uses…
- Tasks and durations (days): A 3; B 4 (after A); C 2 (after A); D 5 (after B and C); E 1 (after C). What is the total slack (float) of task…
- A form has 3 parameters — browser (3 options), OS (3 options) and language (3 options). Exhaustive testing needs 27 combinations. What is…