Under the Hybrid Annuity Model (HAM) for highway projects:

  1. A. Government pays about 40% of cost during construction, the rest as annuities
  2. B. The developer bears the full cost and recovers it by collecting all the toll
  3. C. The government funds the whole cost and the contractor only designs and builds
  4. D. Foreign investors own the highway permanently after paying an upfront fee

Correct answer: A. Government pays about 40% of cost during construction, the rest as annuities

HAM blends EPC and BOT: the authority pays 40% during construction, the developer arranges 60%, and is repaid with interest through annuities; the authority collects the toll. Full toll recovery is BOT (Toll), and full government funding is EPC.

हिंदी में

राजमार्ग परियोजनाओं के लिए हाइब्रिड एन्युइटी मॉडल (HAM) के अंतर्गत:

  1. A. सरकार निर्माण के दौरान लागत का लगभग 40% देती है, शेष वार्षिकियों के रूप में
  2. B. डेवलपर पूरी लागत वहन करता है और पूरा टोल वसूलकर उसे वापस पाता है
  3. C. सरकार पूरी लागत वहन करती है और ठेकेदार केवल डिज़ाइन और निर्माण करता है
  4. D. विदेशी निवेशक अग्रिम शुल्क चुकाकर राजमार्ग के स्थायी स्वामी बन जाते हैं

उत्तर: A. HAM, EPC और BOT का मिश्रण है: प्राधिकरण निर्माण के दौरान 40% देता है, डेवलपर 60% जुटाता है, और ब्याज सहित वार्षिकियों से उसे चुकाया जाता है; टोल प्राधिकरण वसूलता है। पूरा टोल वसूलना BOT (टोल) है, और पूरा सरकारी वित्तपोषण EPC है।