Match the infrastructure model with its description. A. BOT (Toll) B. EPC C. HAM D. TOT; 1. Government funds the project fully; the contractor only designs and builds 2. Government pays about 40% during construction and the rest as annuities 3. Private firm builds, collects toll for the concession period, then hands the asset back 4. Existing public highways are leased for an upfront lump sum, letting the private party collect toll

  1. A. A-3, B-2, C-1, D-4
  2. B. A-3, B-1, C-2, D-4
  3. C. A-4, B-1, C-2, D-3
  4. D. A-3, B-1, C-4, D-2

Correct answer: B. A-3, B-1, C-2, D-4

BOT shifts financing and traffic risk to the private firm; EPC keeps both with the government; HAM splits funding 40:60; Toll-Operate-Transfer monetises highways already built.

हिंदी में

अवसंरचना मॉडल का उसके विवरण से मिलान कीजिए। A. BOT (टोल) B. EPC C. HAM D. TOT; 1. सरकार परियोजना को पूरी तरह वित्त देती है; ठेकेदार केवल डिज़ाइन और निर्माण करता है 2. सरकार निर्माण के दौरान लगभग 40% और शेष वार्षिकियों के रूप में देती है 3. निजी फर्म निर्माण करती है, रियायत अवधि में टोल वसूलती है, फिर परिसंपत्ति लौटा देती है 4. मौजूदा सार्वजनिक राजमार्ग एकमुश्त अग्रिम राशि पर पट्टे पर दिए जाते हैं, जिससे निजी पक्ष टोल वसूलता है

  1. A. A-3, B-2, C-1, D-4
  2. B. A-3, B-1, C-2, D-4
  3. C. A-4, B-1, C-2, D-3
  4. D. A-3, B-1, C-4, D-2

उत्तर: B. BOT वित्तपोषण और यातायात जोखिम निजी फर्म पर डालता है; EPC दोनों सरकार के पास रखता है; HAM वित्तपोषण 40:60 में बाँटता है; टोल-ऑपरेट-ट्रांसफर पहले से बने राजमार्गों का मुद्रीकरण करता है।

More Sectors of the Economy and Government Schemes questions

Exams that ask this topic