Electrical EngineeringHard

Compared with Gauss-Seidel, the Newton-Raphson load flow generally

  1. A. Requires no Jacobian
  2. B. Cannot handle PV buses
  3. C. Needs more iterations
  4. D. Converges in fewer iterations and is less sensitive to system size

Correct answer: D. Converges in fewer iterations and is less sensitive to system size

Quadratic convergence. This is the standard textbook result.