Under the EIA Notification, 2006, the public hearing for a project requiring public consultation is conducted by:

  1. A. The Expert Appraisal Committee of the Union Ministry of Environment
  2. B. The project proponent, through a consultant accredited by the Ministry
  3. C. The State Pollution Control Board or UT Pollution Control Committee
  4. D. The Gram Sabha of the village in which the project is to be located

Correct answer: C. The State Pollution Control Board or UT Pollution Control Committee

The SPCB or UTPCC organises the hearing, chaired by the District Magistrate or an officer not below Additional District Magistrate, and forwards the proceedings to the regulatory authority. The EAC appraises the project afterwards.

हिंदी में

EIA अधिसूचना, 2006 के अंतर्गत, जन परामर्श की आवश्यकता वाली परियोजना की जन सुनवाई कौन आयोजित करता है?

  1. A. केंद्रीय पर्यावरण मंत्रालय की विशेषज्ञ मूल्यांकन समिति
  2. B. परियोजना प्रस्तावक, मंत्रालय द्वारा मान्यता प्राप्त परामर्शदाता के माध्यम से
  3. C. राज्य प्रदूषण नियंत्रण बोर्ड या संघ राज्य क्षेत्र प्रदूषण नियंत्रण समिति
  4. D. उस गाँव की ग्राम सभा जहाँ परियोजना स्थित होनी है

उत्तर: C. SPCB या UTPCC सुनवाई आयोजित करता है, जिसकी अध्यक्षता ज़िला मजिस्ट्रेट या अतिरिक्त ज़िला मजिस्ट्रेट से अन्यून अधिकारी करता है, और कार्यवाही नियामक प्राधिकरण को भेजता है। EAC परियोजना का मूल्यांकन बाद में करती है।