An activity-on-arc project has events S, A, B, C, D, E, T and activities (duration): S→A 3, S→B 2, A→C 4, B→C 6, A→D 2, C→D 3, C→E 5, D→E 1, B→E 4, E→T 2, D→T 6. By how many time units can activity B→E be delayed without delaying the whole project (its total float)?

  1. A. 9
  2. B. 7
  3. C. 4
  4. D. 11

Correct answer: A. 9

Earliest times: S 0, A 3, B 2, C 8, D 11, E 13, T 17. Latest times: T 17, E 15, D 11, C 8, B 2. Total float of B→E = LF(E) − ES(B) − 4 = 15 − 2 − 4 = 9. Using ES(E) instead of LF(E) gives the free float 7.