GeographyHardUPSC Prelims · State PCS
A thermal power station of 500 MW capacity generates 2,628 million units (MU, i.e. GWh) in a non-leap year of 8,760 hours. Its plant load factor is:
- A. 75%
- B. 60%
- C. 66%
- D. 52%
Correct answer: B. 60%
Maximum possible output = 500 MW x 8,760 h = 4,380,000 MWh = 4,380 MU. PLF = 2,628/4,380 = 0.60 = 60%. A common slip is dividing by 5,000 MU (using 10,000 hours) or by 4,000.
हिंदी में
500 MW क्षमता का एक ताप विद्युत केंद्र 8,760 घंटे के एक सामान्य वर्ष में 2,628 मिलियन यूनिट (MU, अर्थात GWh) उत्पादन करता है। इसका संयंत्र भार गुणक (PLF) है:
- A. 75%
- B. 60%
- C. 66%
- D. 52%
उत्तर: B. अधिकतम संभव उत्पादन = 500 MW x 8,760 घंटे = 4,380,000 MWh = 4,380 MU। PLF = 2,628/4,380 = 0.60 = 60%। सामान्य भूल 5,000 MU से (10,000 घंटे मानकर) या 4,000 से भाग देना है।
Practise more Minerals, Energy and Industries questionsMinerals, Energy and Industries: notes and key points
More Minerals, Energy and Industries questions
- A hydel station has an effective head of 50 m and a steady flow of 100 m3/s. If the overall efficiency is 90% and g = 9.8 m/s2, the…
- A cooperative sugar mill crushes 4,000 tonnes of cane a day for 150 days in the season and recovers 10% sugar. Its season output of sugar…
- An aluminium smelter is to make 50,000 tonnes of metal a year. If about 2 tonnes of bauxite give 1 tonne of alumina and about 2 tonnes of…
- A factory uses 5 tonnes of a localised raw material and 3 tonnes of ubiquitous water to make 4 tonnes of product. Its Weberian material…
- In the NCERT classification of industries by ownership, Oil India Limited is cited as an example of the:
- Match each subsidiary of Coal India Limited with its headquarters. A. Bharat Coking Coal B. Central Coalfields C. South Eastern Coalfields…