Under Taylor's differential piece rate, the normal rate is Rs 10 per unit, standard is 20 units a day, and the lower rate is 83% of normal. A worker producing 18 units earns:

  1. A. Rs 180
  2. B. Rs 225
  3. C. Rs 149.40
  4. D. Rs 150

Correct answer: C. Rs 149.40

Below standard the lower rate applies to all units: 18 x 8.30 = Rs 149.40, not the normal Rs 180.