Professional KnowledgeHardIBPS SO IT
In the V-model, unit testing corresponds to which development phase?
- A. Requirements analysis
- B. Detailed (low-level) design
- C. System design
- D. Maintenance
Correct answer: B. Detailed (low-level) design
Each development phase is paired with a test level; units verify low-level design.