Mechanical EngineeringHard
In simple exponential smoothing with alpha = 0.2, the previous forecast is 100 and the actual demand is 120. The new forecast is
- A. 102
- B. 108
- C. 120
- D. 104
Correct answer: D. 104
New forecast = 100 + 0.2 * (120 - 100) = 104.
Practise more Manufacturing, Materials & Industrial Engineering (ISRO Mech) questionsManufacturing, Materials & Industrial Engineering (ISRO Mech): notes and key points
More Manufacturing, Materials & Industrial Engineering (ISRO Mech) questions
- A unity-feedback system with G(s) = K/(s(s + 2)) is required to have a damping ratio of 0.5. The gain K must be
- On a Bode magnitude plot, a double pole at the origin contributes a slope of
- A lead compensator in a control loop
- The eigenvalues of the state matrix A = [[0, 1], [-2, -3]] are
- A surface profile has deviations from the mean line of +2, -3, +1, -2, +4 and -4 micrometres at equally spaced points. The roughness…
- Which non-destructive testing method is best suited to detect subsurface internal flaws in a thick metal casting?