Engineering Mathematics and AptitudeHard

A can complete a job in 12 days and B in 18 days. Working together they finish it in:

  1. A. 6 days
  2. B. 7.2 days
  3. C. 7.5 days
  4. D. 15 days

Correct answer: B. 7.2 days

Combined rate is 1/12 + 1/18 = 5/36 per day, so the time is 36/5 = 7.2 days.