Mechanical EngineeringVery hard
A product needs a total work content of 36 min. The line must make 60 units in an available time of 480 min. Taking the theoretical minimum number of workstations (integer), the line efficiency is
- A. 90.0 %
- B. 56.3 %
- C. 75.0 %
- D. 64.3 %
Correct answer: A. 90.0 %
Cycle time = 480/60 = 8.00 min; N_min = ⌈36/8.00⌉ = 5; η = ΣT/(N·CT) = 90.0%.
Practise more Manufacturing, Industrial Engineering & Materials (Mechanical) questionsManufacturing, Industrial Engineering & Materials (Mechanical): notes and key points
More Manufacturing, Industrial Engineering & Materials (Mechanical) questions
- A plain-carbon steel contains 0.2% carbon. At room temperature, treating ferrite as carbon-free, the fraction of pearlite (0.77% C) in the…
- In a tensile test, the engineering stress is 350 MPa at an engineering strain of 0.1 during uniform deformation. The true stress is
- In a tensile test, the engineering stress is 450 MPa at an engineering strain of 0.15 during uniform deformation. The true stress is
- A turning tool with nose radius 1.2 mm cuts with a feed of 0.1 mm/rev. The theoretical Ra (Ra = f²/(18√3·r)) is
- A turning tool with nose radius 0.8 mm cuts with a feed of 0.15 mm/rev. The theoretical Ra (Ra = f²/(18√3·r)) is
- With rake α = 10° and friction angle β = 30°, Merchant's relation predicts a shear angle of