Mechanical EngineeringHard

A standard time in work measurement is obtained from observed time of 1.5 min, rating 110% and allowances of 10% of normal time as

  1. A. 1.815 min
  2. B. 1.65 min
  3. C. 1.35 min
  4. D. 1.5 min

Correct answer: A. 1.815 min

Normal time = 1.5×1.10 = 1.65; standard time = 1.65×(1 + 0.10) = 1.815 min.