Mechanical EngineeringHard
A standard time in work measurement is obtained from observed time of 1.5 min, rating 110% and allowances of 10% of normal time as
- A. 1.815 min
- B. 1.65 min
- C. 1.35 min
- D. 1.5 min
Correct answer: A. 1.815 min
Normal time = 1.5×1.10 = 1.65; standard time = 1.65×(1 + 0.10) = 1.815 min.