Annual demand is 1000 units, ordering cost Rs 50 per order and holding cost Rs 10 per unit per year. The EOQ is
- A. 50 units
- B. 100 units
- C. 200 units
- D. 141 units
Correct answer: B. 100 units
EOQ = sqrt(2 x 1000 x 50 / 10) = sqrt(10000) = 100.
Practise more Manufacturing, Industrial Engineering & Materials (Mechanical) questionsManufacturing, Industrial Engineering & Materials (Mechanical): notes and key points
More Manufacturing, Industrial Engineering & Materials (Mechanical) questions
- In orthogonal cutting, the uncut chip thickness is 0.2 mm, the chip thickness is 0.4 mm and the tool rake angle is 10°. The shear angle is
- A tool of 15° rake angle cuts a chip of thickness 0.3 mm from an uncut thickness of 0.1 mm (orthogonal cutting). The shear strain in the…
- In orthogonal machining the measured cutting force is 1500 N and thrust force 300 N; the shear angle is 20°. The force along the shear…
- A tool follows Taylor's equation VTⁿ = C with n = 0.2. At 60 m/min the tool life is 90 min. The tool life at 90 m/min is
- A face mill with 4 teeth at 300 rpm and 0.15 mm/tooth cuts a 60 mm wide slab at a depth of 2 mm. The material removal rate is
- A face mill with 4 teeth at 500 rpm and 0.05 mm/tooth cuts a 60 mm wide slab at a depth of 3 mm. The material removal rate is