Budgeted overheads are ₹4,80,000 for 60,000 budgeted machine hours. Actual hours worked are 64,000 and actual overheads ₹5,00,000. What is the over- or under-absorption?

  1. A. Over-absorbed ₹12,000
  2. B. Under-absorbed ₹20,000
  3. C. Under-absorbed ₹12,000
  4. D. Over-absorbed ₹32,000

Correct answer: A. Over-absorbed ₹12,000

Rate = ₹8 an hour; absorbed = 64,000 × 8 = 5,12,000; actual 5,00,000. More was absorbed than incurred: over-absorbed by ₹12,000. Comparing actual with budget gives the misleading ₹20,000.