A cost variance is favourable when:

  1. A. Actual cost exceeds standard cost
  2. B. Actual output falls below the budgeted output
  3. C. Actual cost is below standard cost
  4. D. The standard is revised upward during the year

Correct answer: C. Actual cost is below standard cost

Spending less than the standard for the actual output is favourable; spending more is adverse.