The standard labour rate is ₹50 an hour; 2,000 hours are paid at ₹48 an hour. What is the labour rate variance?

  1. A. ₹4,000 (A)
  2. B. ₹96,000 (F)
  3. C. ₹4,000 (F)
  4. D. ₹3,840 (F)

Correct answer: C. ₹4,000 (F)

Rate variance = actual hours paid × (SR − AR) = 2,000 × (50 − 48) = ₹4,000, favourable because less was paid than standard.