In activity-based costing, which of these is a batch-level activity?

  1. A. Setting up a machine before each production run
  2. B. Power consumed while the machine runs on each unit
  3. C. Insurance of the factory building for the year
  4. D. Designing a new product before it is launched

Correct answer: A. Setting up a machine before each production run

Set-up cost is incurred once per batch, whatever the batch size. Machine power is unit-level (varies with each unit), factory insurance is facility-sustaining, and product design is product-sustaining.