Kaizen costing aims at:

  1. A. Setting a cost ceiling at the design stage from a target price
  2. B. Charging overheads through activities
  3. C. Small, continuous cost reductions during the production phase
  4. D. Comparing actual costs with predetermined standards each month

Correct answer: C. Small, continuous cost reductions during the production phase

Kaizen costing seeks steady incremental savings once a product is in production. Fixing allowable cost at the design stage is target costing; overheads through activities is ABC; comparing against standards is standard costing.