Budgeted fixed overhead is ₹2,00,000 for 10,000 hours (₹20 an hour), with a standard of 2 hours a unit. Actual hours worked are 9,500 and actual output 4,600 units. What is the fixed overhead capacity variance?

  1. A. ₹6,000 (A)
  2. B. ₹16,000 (A)
  3. C. ₹10,000 (F)
  4. D. ₹10,000 (A)

Correct answer: D. ₹10,000 (A)

Capacity variance = (actual hours − budgeted hours) × rate = (9,500 − 10,000) × 20 = ₹10,000 adverse. Efficiency variance = (standard hours 9,200 − actual 9,500) × 20 = ₹6,000 adverse; together they make the ₹16,000 adverse volume variance.