Management & CommerceHardBig 4 · CA Inter level

An asset's decommissioning obligation was recognised at its present value of ₹1,00,000 using an 8% discount rate. Ignoring changes in estimates, what is the finance cost (unwinding of discount) in year 2?

  1. A. ₹8,000
  2. B. ₹16,000
  3. C. ₹9,331
  4. D. ₹8,640

Correct answer: D. ₹8,640

Year 1 unwinding = ₹8,000, taking the provision to ₹1,08,000; year 2 = 8% × 1,08,000 = ₹8,640, charged as finance cost. Repeating ₹8,000 forgets that the discount compounds.