Management & CommerceModerateCA Inter level · Bank MT
Under Taylor's differential piece-rate system, the standard is 40 units a day and the normal rate ₹5 a unit; output below standard is paid at 80% of the rate and at or above standard at 120%. A worker produces 42 units. What does he earn?
- A. ₹210
- B. ₹252
- C. ₹168
- D. ₹201.60
Correct answer: B. ₹252
At or above standard he gets 120% of ₹5 = ₹6 a unit on all units: 42 × 6 = ₹252. ₹168 applies the low rate (₹4) to the full 42 units.
Practise more Financial & Cost Accounting questionsFinancial & Cost Accounting: notes and key points
More Financial & Cost Accounting questions
- A purchase of ₹4,500 from Mohan was entered in the purchases book as ₹5,400 and posted from there. What is the effect, and what is the…
- A machine costing ₹5,00,000 is bought by issuing equity shares worth ₹3,00,000 and paying ₹2,00,000 in cash. What appears in the cash-flow…
- A firm's average profit before tax is ₹3,00,000; the tax rate is 25%; capital employed is ₹15,00,000 and the normal rate of return (after…
- After the year end but before the financial statements are approved, management decides to liquidate the company because its main customer…
- A, B and C change their profit ratio from 5 : 3 : 2 to 4 : 3 : 3. Goodwill is valued at ₹2,00,000 and is not to appear in the books. What…
- An asset costing ₹3,10,000 (residual ₹10,000, life 5 years) is bought on 1 October 2022 and depreciated by the sum-of-the-years'-digits…